Limited development zone in Queensland — what you can build

Land with a serious constraint — flooding, bushfire, steep slopes, or sensitive environment — where councils limit what can happen. A house may be possible, but expect closer checks and fewer options to subdivide or intensify.

In short: A house on an existing lot may be accepted or code assessed; more intensive use usually needs a development application. The table below gives the real answer, council by council.

What the tables of assessment say, council by council

Each council's planning scheme has a table of assessment: for every zone and every kind of project, it says whether you need no application, or a development application and how it is assessed. Each coloured tag links to that council's page for the project. Read from 11 councils.

What the tags mean

  • Accepted — no planning application needed.
  • Accepted if requirements met — no application if your plans meet the council's code requirements; if they do not, it becomes a development application.
  • Code — a development application assessed against the planning codes, without public notification.
  • Impact — a development application with public notification: neighbours can make submissions and object. How to object to a development application.
  • Not allowed — the planning scheme does not allow it in this zone.

“Varies” means the table depends on the details of the project. An overlay such as flood or bushfire can turn an accepted project into a development application — see planning overlays explained.

Common questions

Can I build a granny flat in the limited development zone?

It varies by council. Across the 11 councils whose tables of assessment we have read, the most common answer for a granny flat in this zone is a development application with public notification (impact assessment). The split was: 4 accepted if requirements met, 2 code, 7 impact (each council zone counted once). Check your own council's table on this page, and whether an overlay such as flood or bushfire applies to your lot.

Do I need approval for a dual occupancy in the limited development zone?

It varies by council. Across the 11 councils whose tables of assessment we have read, the most common answer for a dual occupancy in this zone is a development application with public notification (impact assessment). The split was: 13 impact (each council zone counted once). Check your own council's table on this page, and whether an overlay such as flood or bushfire applies to your lot.

Can I subdivide land in the limited development zone?

It varies by council. Across the 11 councils whose tables of assessment we have read, the most common answer for subdividing in this zone is a development application assessed against the codes (code assessment). The split was: 10 code, 3 impact (each council zone counted once). Check your own council's table on this page, and whether an overlay such as flood or bushfire applies to your lot.

Is your lot in this zone?

A Landbrief site report checks any Queensland address against its zone and every planning layer that applies — $49 as a PDF. Check an address.