Demolishing a building in Gladstone — do you need approval?

Gladstone Regional Council's planning scheme — the Gladstone Regional Council Planning Scheme (Version 2.1) — decides whether demolition needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.

In a low density residential zone

No planning approval needed. Demolishing a building needs no planning development application in the Low density residential zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required).

I don't know my zone — choose my council instead

The zone is on your rates notice, or a Landbrief site report will find it for you.

Zone by zone

Building work (demolition). Residential zones first.

ZoneWhat the table saysConditionsWhat you'll need
Low density residential zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Low density residential zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Low–medium density residential zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Low–medium density residential zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Medium density residential zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Medium density residential zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Character residential zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Character residential zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Rural residential zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Rural residential zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Emerging community zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Emerging community zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Township zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Township zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Centre zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Centre zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Community facilities zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Community facilities zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Conservation zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Conservation zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Environmental management zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Environmental management zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Industry investigation zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Industry investigation zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Limited development zone (constrained land) No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Limited development zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Low impact industry zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Low impact industry zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Major tourism zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Major tourism zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Medium impact industry zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Medium impact industry zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Minor tourism zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Minor tourism zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Mixed use zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Mixed use zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Neighbourhood centre zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Neighbourhood centre zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Open space zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Open space zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Principal centre zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Principal centre zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Rural zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Rural zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Special industry zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Special industry zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Special purpose zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Special purpose zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Specialised centre zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Specialised centre zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval
Sport and recreation zone No planning approval needed Section 5.7 Demolishing a building needs no planning development application in the Sport and recreation zone unless it is a local heritage place, where demolition needs an impact assessable application (a demolition building approval is still required). Building approval

Overlays that change the answer

  • Heritage overlay (local heritage place). On a local heritage place: a change of use that would be accepted subject to requirements and involves building work becomes code assessable; any building work not associated with a change of use (including minor work) is code assessable; demolition, partial demolition or removal is impact assessable; operational work changing landscaping, fencing or natural features named in the citation is code assessable. Work under a Queensland Heritage Act exemption certificate is accepted. (Table 5.10.1 Heritage overlay code)

Worth knowing in Gladstone

Gladstone Regional Council Planning Scheme (Version 2.1), Part 5, converted from the council's PDF (not an official copy). A material change of use is impact assessable unless the table says otherwise or the use isn't listed; reconfiguring a lot is code assessable unless Table 5.6.1 says otherwise; building work and operational work are accepted unless the tables say otherwise (section 5.3.2). Building work (section 5.7): for a dwelling house there is 'no change to assessment category' against the relevant zone code, and no other building work is regulated unless an overlay table says so — so sheds, extensions, pools, fences and demolition need no planning development application outside overlays (mainly the Heritage overlay); a building approval under the Building Act is still needed. Accepted development subject to requirements that doesn't meet the listed acceptable outcomes becomes code assessable (section 5.3.3). Schedule 6 of the Planning Regulation (Table 5.4.1) can make a dwelling house or community residence accepted development regardless of the zone tables; Table 5.4.2 lets a one-into-two-lot subdivision in a residential or industry zone (not rural residential) be code assessable under schedule 10, part 12 of the Regulation against schedule 12 benchmarks. Precincts: Medium density residential — Beaches Village Circuit (dwelling house and dual occupancy impact assessable; 1,000 m² lots) and Gladstone West Hospital (shop/office/café code); Low density residential — Calliope neighbourhood (800 m² lots); Mixed use — Jeffery Court (office and some other uses lose their code/accepted pathway); Specialised centre — Clinton and Central Gladstone / Toolooa Street east (the only places retail/office uses are listed); Low impact industry — Hanson Road (showrooms, hardware); Medium impact industry — Red Rover Road (structure-plan pathway); Rural residential — Bicentennial Drive Enterprise; Sport and recreation — Benaraby Motor Sport; Special purpose — Gladstone Airport; Limited development — Flood affected lands (dwelling house code assessable, home based business accepted subject to requirements) and Major industry buffer. There are no local plans (section 5.9). Operational work: earthworks of 100 m³ or more are code assessable in all zones (Rural zone: 500 m³ for water retention, 100 m³ otherwise, accepted subject to requirements); the Coastal hazard and Flood hazard overlays make filling or excavation over 50 m³ code assessable. The Coastal hazard, Hazardous activities, Steep land, Scenic amenity and Water resource catchment overlays don't change the category but add their own acceptable outcomes to accepted development subject to requirements (code assessable if not met). Where land is in more than one zone or overlay, the highest category applies, and an overlay's category overrides the zone's (section 5.3.2).

What Gladstone Regional Council publishes

These come from the council's own website and planning scheme, read on 18 November 2026. Each one links to the page it came from. Councils change their rules and fees, so open the source before you rely on a figure.

Local heritage place
Building work that involves demolishing, partly demolishing or removing a local heritage place is impact assessable against the Heritage overlay code. (Applies to: Local heritage places (Heritage overlay).) Gladstone Regional Council Planning Scheme (Our Place Our Plan) Version 2.1, Part 5 Tables of assessment (Heritage overlay)
Demolition fee and bond 2026-27
The 2026-27 council building certification fees to demolish a Class 1 or Class 10 building are $222.00 lodgement plus $432.00 building fee, with a $6,621.00 demolition bond that is refundable after a satisfactory final inspection. (Applies to: Class 1 (houses) and Class 10 buildings, where Council is the building certifier.) Fees and Charges Register 2026/27: Development Services (Gladstone Regional Council)
Sewer capping fee and bond 2026-27
For capping a sewer because of a demolition, the 2026-27 fees are $166.00 lodgement and $227.00 inspection, with a $6,621.00 capping of sewer bond in Council sewered areas, refundable after a satisfactory final inspection. (Applies to: Properties in a Council sewered area.) Fees and Charges Register 2026/27: Development Services (Gladstone Regional Council)
Relocating a house
Relocating a house needs a building approval and may also need planning, amenity and aesthetics, or boundary relaxation approval from Council. (Applies to: Houses relocated within or into the Gladstone Region.) New and Relocated Homes (Gladstone Regional Council web page)
Asbestos report for relocated houses
A relocated house needs a report from a licensed asbestos contractor showing the building is free from asbestos. (Applies to: Houses being relocated.) New and Relocated Homes (Gladstone Regional Council web page)
Asbestos disposal
Council accepts up to 10 square metres, or under 175kg, of material containing asbestos free of charge from property owners or owner-builders at Gladstone Transfer Station and Benaraby Landfill. A Disposal Conditions and Application Form is needed. (Applies to: Domestic asbestos from within the Gladstone Region.) Landfill Bin and Waste Disposal (Gladstone Regional Council web page)

The statewide rules

These apply across Queensland. Whether the council also needs to approve the demolition depends on your address: a heritage listing or a character overlay in the planning scheme is what brings it in.

Building approval
Demolishing a building is building work under the Building Act 1975, so it needs a building approval from a private certifier or the council. The regulation's list of work that needs no approval has no entry for demolishing a house.
Time limits
Once a demolition approval is given, the work must substantially start within 2 months and be finished within 1 year.
Local heritage places
Development on a place in a council's local heritage register is assessable across Queensland, so demolishing one needs a development application to the council.
Character and pre-war housing areas
There is no statewide rule. A council's planning scheme decides whether demolishing an older house in a character area needs a development application. Where a scheme does make demolishing a home assessable, a private certifier must hold the building approval documents for 5 business days before giving them to the applicant.
State heritage places
Any development on a place in the Queensland Heritage Register needs a development approval assessed by the State, unless an exemption certificate has been given. Exemption certificates are for work with little or no effect on the place.
Asbestos: licensed removal
A contractor needs an asbestos removal licence to remove more than 10 m² of bonded (non-friable) asbestos, and a class A licence for any friable asbestos. Asbestos must be removed before demolition starts, as far as is reasonably practicable.
Asbestos: doing it yourself
A homeowner can remove up to 10 m² of bonded asbestos. More than 10 m² needs a certificate from a Queensland Health-approved course. A homeowner can never remove friable asbestos.
Notice to Workplace Health and Safety Queensland
The contractor must give written notice at least 5 days before demolishing a structure that is at least 6 m high, or any demolition that uses load-shifting machinery on a suspended floor or explosives.
Sewer and water
Sealing the sewer drain of an existing building is notifiable plumbing work, done by a licensed plumber or drainer. Councils and water providers set their own disconnection steps and fees.
  • A building approval for demolition and a development application are separate. A certifier can't replace the council's decision where the planning scheme or a heritage listing requires one.

What else you'll need

  • Building approval

More about Gladstone

Other projects in Gladstone

Granny flatDual occupancySubdivideShed or carportExtensionPoolFence or wallHome businessTownhousesShop, café or officeClear trees

The statewide position on this project: Demolish in Queensland.

Read from the Gladstone Regional Council Planning Scheme (Version 2.1) tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.