Demolishing a building in Gold Coast — do you need approval?
City of Gold Coast's planning scheme — the Gold Coast City Plan (City Plan) — Part 5 Tables of assessment (v14, 2026-09-29) — decides whether demolition needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.
In a low density residential zone
No planning approval needed. Demolishing a building is accepted development under the planning scheme unless an overlay (such as heritage) applies, but a building approval for demolition is still required.
I don't know my zone — choose my council instead
The zone is on your rates notice, or a Landbrief site report will find it for you.
Zone by zone
Building work (demolition). Residential zones first.
| Zone | What the table says | Conditions | What you'll need |
|---|---|---|---|
| Low density residential zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development under the planning scheme unless an overlay (such as heritage) applies, but a building approval for demolition is still required. | Building approval |
| Medium density residential zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development under the planning scheme unless an overlay (such as heritage) applies, but a building approval for demolition is still required. | Building approval |
| High density residential zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development under the planning scheme unless an overlay (such as heritage) applies, but a building approval for demolition is still required. | Building approval |
| Emerging community zone | No planning approval needed Table 5.7.1 | Demolition is not triggered as assessable by the City Plan unless an overlay (e.g. heritage) applies, though a building approval is still required. | Building approval |
| Rural residential zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development unless an overlay such as heritage applies, though a building approval is still required. | Building approval |
| Township zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development under the planning scheme unless a heritage or other overlay applies, though you still need a building approval. | Building approval |
| Centre zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development under the planning scheme unless an overlay (such as heritage) applies, but a building approval for demolition is still required. | Building approval |
| Community facilities zone | No planning approval needed Table 5.7.1 | Demolition is not triggered as assessable by the City Plan unless an overlay (e.g. heritage) applies, though a building approval is still required. | Building approval |
| Conservation zone | No planning approval needed Table 5.7.1 | Demolition is accepted development under the planning scheme (an overlay such as heritage could change this), but you still need a building approval. | Building approval |
| Extractive industry zone | No planning approval needed Table 5.7.1 | Demolition is not triggered as assessable by the City Plan unless an overlay (e.g. heritage) applies, though a building approval is still required. | Building approval |
| High impact industry zone | No planning approval needed Table 5.7.1 | Demolition is accepted building work unless an overlay (such as heritage) applies, but a building approval is still required. | Building approval |
| Innovation zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development under the planning scheme unless a heritage or other overlay applies, though you still need a building approval. | Building approval |
| Limited development (constrained land) zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development under the planning scheme unless a heritage or other overlay applies, though you still need a building approval. | Building approval |
| Low impact industry zone | No planning approval needed Table 5.7.1 | Demolition is accepted building work unless an overlay (such as heritage) applies, but a building approval is still required. | Building approval |
| Major tourism zone | No planning approval needed Table 5.7.1 | Demolition is not triggered as assessable by the City Plan unless an overlay (e.g. heritage) applies, though a building approval is still required. | Building approval |
| Medium impact industry zone | No planning approval needed Table 5.7.1 | Demolition is accepted building work unless an overlay (such as heritage) applies, but a building approval is still required. | Building approval |
| Mixed use zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development under the planning scheme unless a heritage or other overlay applies, though you still need a building approval. | Building approval |
| Neighbourhood centre zone | No planning approval needed Table 5.7.1 | Demolition is accepted development under the planning scheme (an overlay such as heritage could change this), but you still need a building approval. | Building approval |
| Open space zone | No planning approval needed Table 5.7.1 | Demolition is accepted development under the planning scheme (an overlay such as heritage could change this), but you still need a building approval. | Building approval |
| Rural zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development unless an overlay such as heritage applies, though a building approval is still required. | Building approval |
| Special purpose zone | No planning approval needed Table 5.7.1 | Demolishing a building is accepted development unless an overlay such as heritage applies, though a building approval is still required. | Building approval |
| Sport and recreation zone | No planning approval needed Table 5.7.1 | Demolition is accepted development under the planning scheme (an overlay such as heritage could change this), but you still need a building approval. | Building approval |
| Waterfront and marine industry zone | No planning approval needed Table 5.7.1 | Demolition is accepted building work unless an overlay (such as heritage) applies, but a building approval is still required. | Building approval |
Overlays that change the answer
- Heritage overlay. In a 'Local heritage place', building work that does not demolish/relocate/remove becomes code assessable; building work that partly or fully demolishes/relocates/removes becomes impact assessable (a development application that may be publicly notified). Essential repair/maintenance under the Queensland Heritage Act is unchanged. Operational work becomes code assessable. In a 'Place in proximity to a local heritage place', new buildings/extensions can become code assessable. (Table 5.10.12 Heritage overlay)
Worth knowing in Gold Coast
Precinct variations within zones can change answers materially: e.g. the Low density residential and Township 'Large lot' precincts allow no additional subdivision lots and have their own MCU tables; the Calypso Bay precinct lowers the Low density residential minimum to 400m²; Future industry precincts require 20ha; the Rural 'Rural landscape and environment' and Rural residential 'landscape and environment' precincts prohibit/limit new lots. Subdivision thresholds use the Residential density overlay (RD1–RD8) in medium/high density residential zones and the Minimum lot size overlay map elsewhere — always check the overlay maps for the specific lot. Schedule 12 'one into two' subdivision does NOT apply anywhere in Gold Coast because the whole city is affected by overlays, so all genuine subdivision is at least code assessable. For all building work (sheds, pools, fences, extensions, demolition) a separate building approval under the Building Act 1975 is also required even where no planning (City Plan) approval is needed. State Vegetation Management Act rules for clearing are separate from the City Plan Vegetation management code. The Special purpose zone is largely regulated by other legislation (see Part 10); the Special development area precinct makes any use impact assessable. Note multiple overlays can apply to one site and the most onerous category prevails.
What City of Gold Coast publishes
These come from the council's own website and planning scheme, read on 18 November 2026. Each one links to the page it came from. Councils change their rules and fees, so open the source before you rely on a figure.
- Asbestos: where it is accepted
- Council accepts asbestos only at Stapylton landfill (7 days a week, before 2pm) and Reedy Creek landfill (Monday to Friday before 2pm and Saturday before 11am). (Applies to: Asbestos waste.) Disposal of asbestos (City of Gold Coast web page)
- Asbestos: homeowner limits
- Homeowners can remove less than 10 square metres (up to 250 kilograms) of non-friable asbestos without Queensland Health approval, and can transport up to 175 kilograms of non-friable asbestos without an environmental authority. (Applies to: Non-friable asbestos removed by a homeowner.) Disposal of asbestos (City of Gold Coast web page)
- Asbestos: packaging
- Asbestos taken to a council landfill must be wet down and double-wrapped in low-density polyethylene sheets at least 0.2 millimetres thick, in bags no larger than 1.2 metres by 0.9 metres and no heavier than 25 kilograms. (Applies to: Asbestos loads taken to Stapylton or Reedy Creek landfill.) Disposal of asbestos (City of Gold Coast web page)
- Asbestos: disposal fee
- The asbestos disposal fee for waste from inside City limits is $346 per tonne, with an $83 minimum charge for up to 240 kg. (Applies to: Asbestos from inside City of Gold Coast limits.) Waste disposal fees (City of Gold Coast web page)
The statewide rules
These apply across Queensland. Whether the council also needs to approve the demolition depends on your address: a heritage listing or a character overlay in the planning scheme is what brings it in.
- Building approval
- Demolishing a building is building work under the Building Act 1975, so it needs a building approval from a private certifier or the council. The regulation's list of work that needs no approval has no entry for demolishing a house.
- Time limits
- Once a demolition approval is given, the work must substantially start within 2 months and be finished within 1 year.
- Local heritage places
- Development on a place in a council's local heritage register is assessable across Queensland, so demolishing one needs a development application to the council.
- Character and pre-war housing areas
- There is no statewide rule. A council's planning scheme decides whether demolishing an older house in a character area needs a development application. Where a scheme does make demolishing a home assessable, a private certifier must hold the building approval documents for 5 business days before giving them to the applicant.
- State heritage places
- Any development on a place in the Queensland Heritage Register needs a development approval assessed by the State, unless an exemption certificate has been given. Exemption certificates are for work with little or no effect on the place.
- Asbestos: licensed removal
- A contractor needs an asbestos removal licence to remove more than 10 m² of bonded (non-friable) asbestos, and a class A licence for any friable asbestos. Asbestos must be removed before demolition starts, as far as is reasonably practicable.
- Asbestos: doing it yourself
- A homeowner can remove up to 10 m² of bonded asbestos. More than 10 m² needs a certificate from a Queensland Health-approved course. A homeowner can never remove friable asbestos.
- Notice to Workplace Health and Safety Queensland
- The contractor must give written notice at least 5 days before demolishing a structure that is at least 6 m high, or any demolition that uses load-shifting machinery on a suspended floor or explosives.
- Sewer and water
- Sealing the sewer drain of an existing building is notifiable plumbing work, done by a licensed plumber or drainer. Councils and water providers set their own disconnection steps and fees.
- A building approval for demolition and a development application are separate. A certifier can't replace the council's decision where the planning scheme or a heritage listing requires one.
- Building Act 1975, sections 5 (building work), 20 (assessable building work), 71 (time limits for demolition) and 88 (the 5 business day hold)
- Planning Regulation 2017, Schedule 10, sections 14 (local heritage places) and 15 (Queensland heritage places)
- Work Health and Safety Regulation 2011, sections 142 (notice of demolition work), 452, 458, 485 and 487 (asbestos)
- Public Health Regulation 2018, sections 7 and 8 — asbestos removal by homeowners
- Homeowner's certificate to remove asbestos — Queensland Government
- Plumbing and Drainage Regulation 2019, Schedule 1 — notifiable work
What else you'll need
- Building approval
More about Gold Coast
- What can you build in Gold Coast? Council overview and development applications
- Every Queensland zone explained, with what each council allows and the planning overlays that change the answer
- What City of Gold Coast charges for a development application, compared with other councils
- A Landbrief site report for your Gold Coast address — every planning layer that applies to the lot
- Development applications in Southport
- Development applications in Surfers Paradise
- Development applications in Palm Beach
- Development applications in Burleigh Heads
- Development applications in Coomera
- Development applications in Mermaid Waters
- Development applications in Upper Coomera
- Development applications in Broadbeach Waters
Other projects in Gold Coast
Granny flatDual occupancySubdivideShed or carportExtensionPoolFence or wallHome businessTownhousesShop, café or officeClear trees
The statewide position on this project: Demolish in Queensland.
Read from the Gold Coast City Plan (City Plan) — Part 5 Tables of assessment (v14, 2026-09-29) tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.