landbrief.

Townhouses and units in Rockhampton — do you need approval?

Rockhampton Regional Council's planning scheme — the Rockhampton Region Planning Scheme 2015 (Version 5, 2025-03-28) — decides whether townhouses needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.

In a low density residential zone

Needs a development application (code assessment). Townhouses/units need a code-assessed development application only if close to a centre and on a suitable road; otherwise an impact-assessed application is required.

I don't know my zone — choose my council instead

The zone is on your rates notice, or a Landbrief site report will find it for you.

Zone by zone

Multiple dwelling. Residential zones first.

ZoneWhat the table saysConditionsWhat you'll need
Low density residential zone Needs a development application (code assessment) Table 5.4.1.1 if within 200 m of a centre/open space/sport zone, major hospital or CQ University, and on a road classified minor urban collector or higherIf not met: a development application with impact assessment (neighbours can make submissions). Building approvalAssessed against: Low density residential zone code, Access, parking and transport code, Landscape code, Stormwater management code, Waste management code, Water and sewer code
Low density residential zone — Fitzroy River accommodation precinct Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.1.1.1 multiple dwelling is not listed for this precinct Building approvalAssessed against: The planning scheme
Low density residential zone — Residential stables precinct Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.1.1.2 multiple dwelling is not listed for this precinct Building approvalAssessed against: The planning scheme
Low-medium density residential zone Needs a development application (code assessment) Table 5.4.1.2 multiple dwelling Building approvalAssessed against: Low-medium density residential zone code, Access, parking and transport code, Landscape code, Stormwater management code, Waste management code, Water and sewer code
High density residential zone Accepted if you meet the requirements Table 5.4.1.3 if reusing existing building(s) with no more than minor building workIf not met: a development application with code assessment. Building approvalAssessed against: High density residential zone code, Works code, Access, parking and transport code, Landscape code, Stormwater management code, Waste management code, Water and sewer code
Rural residential zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.6.5 Townhouses or units (multiple dwelling) are not listed in this zone, so they fall under 'any other use' and need an impact-assessable development application. Building approvalAssessed against: The planning scheme
Township zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.6.7 Multiple dwellings (townhouses or units) are not listed in the Township zone, so the default 'any other use' row applies and an impact-assessable development application is required. Building approvalAssessed against: The planning scheme
Emerging community zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.6.2 Multiple dwellings (townhouses/units) are not listed for the Emerging community zone, so they default to an impact-assessable development application. Building approvalAssessed against: The planning scheme
Community facilities zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.6.1 Multiple dwellings (townhouses/units) are not listed for the Community facilities zone, so they default to an impact-assessable development application. Building approvalAssessed against: The planning scheme
District centre zone Accepted if you meet the requirements Table 5.4.2.3 if reusing existing building(s) with no more than minor building workIf not met: a development application with code assessment. Building approvalAssessed against: District centre zone code, Works code, Access, parking and transport code, Landscape code, Stormwater management code, Waste management code, Water and sewer code
Environmental management and conservation zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.4.1 Townhouses or units (multiple dwelling) are not listed in this zone, so they fall under 'any other use' and need an impact-assessable development application. Building approvalAssessed against: The planning scheme
High impact industry zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.5.3 Multiple dwellings are not listed in the High impact industry zone, so they default to impact assessment and need a development application. Building approvalAssessed against: The planning scheme
Limited development (constrained land) zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.6.3 Townhouses or units (multiple dwelling) are not listed in this zone, so they fall under 'any other use' and need an impact-assessable development application. Building approvalAssessed against: The planning scheme
Local centre zone Accepted if you meet the requirements Table 5.4.2.4 Multiple dwelling — if the reuse of existing building(s) or structure(s) and not involving more than minor building workIf not met: a development application with code assessment. Building approvalAssessed against: Local centre zone code, Works code
Low impact industry zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.5.1 Multiple dwellings are not listed in the Low impact industry zone, so they default to impact assessment and need a development application. Building approvalAssessed against: The planning scheme
Major centre zone Accepted if you meet the requirements Table 5.4.2.2 if reusing existing building(s) with no more than minor building workIf not met: a development application with code assessment. Building approvalAssessed against: Major centre zone code, Works code, Access, parking and transport code, Landscape code, Stormwater management code, Waste management code, Water and sewer code
Medium impact industry zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.5.2 Multiple dwellings are not listed in the Medium impact industry zone, so they default to impact assessment and need a development application. Building approvalAssessed against: The planning scheme
Neighbourhood centre zone Accepted if you meet the requirements Table 5.4.2.5 Multiple dwelling — if the reuse of existing building(s) or structure(s) and not involving more than minor building workIf not met: a development application with code assessment. Building approvalAssessed against: Neighbourhood centre zone code, Works code
Open space zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.3.2 Multiple dwellings are not listed in the Open space zone, so they default to impact assessment and need a development application. Building approvalAssessed against: The planning scheme
Principal centre zone Accepted if you meet the requirements Tables 5.4.2.1.1–5.4.2.1.4 if reusing existing building(s) with no more than minor building work (not in Denison Street precinct where multiple dwelling is not listed and defaults to impact)If not met: a development application with code assessment. Building approvalAssessed against: Principal centre zone code, Works code, Access, parking and transport code, Landscape code, Stormwater management code, Waste management code, Water and sewer code
Rural zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.6.4 Townhouses or units (multiple dwelling) are not listed in this zone, so they fall under 'any other use' and need an impact-assessable development application. Building approvalAssessed against: The planning scheme
Special industry zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.5.4 Multiple dwellings (townhouses/units) are not listed for the Special industry zone, so they default to an impact-assessable development application. Building approvalAssessed against: The planning scheme
Special purpose zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.6.6 Multiple dwellings (townhouses or units) are not listed in the Special purpose zone, so the default 'any other use' row applies and an impact-assessable development application is required. Building approvalAssessed against: The planning scheme
Specialised centre zone It depends — see below Table 5.4.2.6.1/5.4.2.6.2 Multiple dwelling — accepted subject to requirements/code if located in the relevant residential/mixed-use sub-precinct and reusing existing building; otherwise impactIf not met: a development application with impact assessment (neighbours can make submissions). Building approvalAssessed against: Specialised centre zone code, Works code, The planning scheme
Sport and recreation zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.3.1 Multiple dwelling not listed; defaults to 'any other use' Building approvalAssessed against: The planning scheme
Waterfront and marine industry zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.4.5.5 Multiple dwellings (townhouses/units) are not listed for the Waterfront and marine industry zone, so they default to an impact-assessable development application. Building approvalAssessed against: The planning scheme

Overlays that change the answer

Worth knowing in Rockhampton

IMPORTANT: The scheme's building work table (section 5.6) is 'Not applicable' — the scheme does NOT itself make domestic building work (sheds, carports, pools, fences, extensions, demolition) assessable in the base case. Those projects are generally 'accepted' under the planning scheme (no planning development application), but a building approval under the Building Act 1975 is almost always still required and must be obtained separately. Overlays (especially Flood, Character, Heritage) can change this — see overlay_triggers. Granny flats: the QPP 'Dwelling house' definition includes a secondary dwelling, so a granny flat follows the Dwelling house row of each zone; in residential/township/rural/rural residential/emerging community zones a dwelling house is 'accepted' (or 'accepted subject to requirements' in Emerging community and Rural), but in centre, industry, open space, sport & recreation, community facilities, special purpose, limited development and environmental zones a dwelling house is not listed and falls to the 'any other use' row = impact assessable. Minimum lot sizes for subdivision are set in Table 9.3.5.3.2 of the Reconfiguring a lot code, which was not reproduced in the material provided — specific numeric minimums per zone could not be extracted, so min_lot_size_m2 is null for all zones. Known thresholds: Emerging community = 10 hectares for code assessment; Rural = the minimum nominated in the Reconfiguring a lot code. Many zones have precincts and sub-precincts; the scheme states that for a precinct/sub-precinct the relevant (parent) zone categories apply for reconfiguring and operational work, but material-change-of-use tables can differ by precinct (e.g. Low density residential Fitzroy River accommodation precinct allows some small-scale commercial uses). Tree clearing: the scheme only regulates vegetation clearing as operational work via overlays (Biodiversity, etc.); the general operational work table (5.7.1) mainly covers filling/excavation and access/services works — most vegetation clearing is accepted under the scheme but the State Vegetation Management Act 1999 rules are separate and may still apply. Home-based business is 'accepted subject to requirements' in residential, township, rural, rural residential, industry and emerging community zones (meet the relevant zone code) and 'accepted' in centre zones.

What else you'll need

  • Building approval

More about Rockhampton

Other projects in Rockhampton

Granny flatDual occupancySubdivideShed or carportExtensionPoolFence or wallHome businessShop, café or officeClear treesDemolish

The statewide position on this project: Townhouses in Queensland.

Read from the Rockhampton Region Planning Scheme 2015 (Version 5, 2025-03-28) tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.