Demolishing a building in Scenic Rim — do you need approval?

Scenic Rim Regional Council's planning scheme — the Scenic Rim Planning Scheme 2020 — decides whether demolition needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.

In a low density residential zone

No planning approval needed. The planning scheme does not regulate building work, so demolition needs no planning approval unless a heritage overlay applies (a Building Act approval may still be required).

I don't know my zone — choose my council instead

The zone is on your rates notice, or a Landbrief site report will find it for you.

Zone by zone

Building work (demolition). Residential zones first.

ZoneWhat the table saysConditionsWhat you'll need
Low Density Residential Zone No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning approval unless a heritage overlay applies (a Building Act approval may still be required). Building approval
Low-medium Density Residential Zone No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning approval unless a heritage overlay applies (a Building Act approval may still be required). Building approval
Emerging Community Zone No planning approval needed 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies (a Building Act approval may still be required). Building approval
Rural Residential Zone - (Where no precinct applies) No planning approval needed 5.7 Demolition is building work not regulated by the planning scheme, so no planning approval is needed (a building permit and heritage checks may still apply). Building approval
Rural Residential Zone - Rural Residential A Precinct No planning approval needed 5.7 Demolishing a building needs no planning development application because the scheme regulates no building work, though a building approval and heritage checks may still apply. Building approval
Township Zone - (Where no precinct applies) No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies (a building approval under the Building Act may still be required). Building approval
Township Zone - Township Residential Precinct No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies, though a building approval is still required. Building approval
Community Facilities Zone No planning approval needed 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies (a Building Act approval may still be required). Building approval
Conservation Zone No planning approval needed 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies (a Building Act approval may still be required). Building approval
District Centre Zone No planning approval needed 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies (a Building Act approval may still be required). Building approval
Industry Zone No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning approval under the scheme (a building/heritage approval may still be required). Building approval
Limited Development Zone - (Where no precinct applies) No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning approval under the scheme (a building/heritage approval may still be required). Building approval
Limited Development Zone - Flood Land Precinct No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning approval under the scheme (a building/heritage approval may still be required). Building approval
Limited Development Zone - Historical Subdivision Precinct No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning approval under the scheme (a building/heritage approval may still be required). Building approval
Local Centre Zone No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning approval unless a heritage overlay applies (a Building Act approval may still be required). Building approval
Major Centre Zone No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning approval unless a heritage overlay applies (a Building Act approval may still be required). Building approval
Major Tourism Zone No planning approval needed 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application (a building approval and overlay checks such as heritage may still apply). Building approval
Minor Tourism Zone No planning approval needed 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application (a building approval and overlay checks such as heritage may still apply). Building approval
Mixed Use Zone No planning approval needed 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application (a building approval and overlay checks such as heritage may still apply). Building approval
Mixed Use Zone - Commercial Industry Precinct No planning approval needed 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application (a building approval and overlay checks such as heritage may still apply). Building approval
Neighbourhood Centre Zone No planning approval needed 5.7 Demolition is building work not regulated by the planning scheme, so no planning approval is needed (a building permit and heritage overlay checks may still apply). Building approval
Recreation and Open Space Zone - (Where no precinct applies) No planning approval needed 5.7 Demolition is building work not regulated by the planning scheme, so no planning approval is needed (a building permit and heritage checks may still apply). Building approval
Recreation and Open Space Zone - Passive Recreation Precinct No planning approval needed 5.7 Demolition is building work not regulated by the planning scheme, so no planning approval is needed (a building permit and heritage checks may still apply). Building approval
Rural Zone - (Where no precinct applies) No planning approval needed 5.7 Demolishing a building needs no planning development application because the scheme regulates no building work, though a building approval and heritage checks may still apply. Building approval
Rural Zone - Rural Escarpment Protection Precinct No planning approval needed 5.7 Demolishing a building needs no planning development application because the scheme regulates no building work, though a building approval and heritage checks may still apply. Building approval
Rural Zone - Tamborine Mountain Rural Precinct No planning approval needed 5.7 Demolishing a building needs no planning development application because the scheme regulates no building work, though a building approval and heritage checks may still apply. Building approval
Special Purpose Zone - (Where no precinct applies) No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies (a building approval under the Building Act may still be required). Building approval
Special Purpose Zone - Bromelton State Development Area Precinct No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies (a building approval under the Building Act may still be required). Building approval
Special Purpose Zone - Bulk Water Storage Facilities Precinct No planning approval needed Section 5.7 The planning scheme does not regulate building work, so demolition needs no planning development application unless a heritage overlay applies (a building approval under the Building Act may still be required). Building approval

Overlays that change the answer

  • Airport Environs and Defence Land Overlay (OM-02). Building work and material change of use in the Height Restriction Zone, Wildlife Buffer Area or Building Restricted Area become Accepted subject to requirements against the Airport Environs and Defence Land Overlay Code; other uses in the Defence Land Buffer Area and reconfiguring a lot become code assessable. (5.10 Airport Environs and Defence Land Overlay Map OM-02)
  • Local Heritage Overlay (OM-08). In a Local Heritage Place, material change of use, reconfiguring a lot, and building work or operational work not associated with an MCU all become code assessable against the Local Heritage Overlay Code (so renovations, outbuildings and demolition need a development application). (5.10 Local Heritage Overlay Map OM-08)

Worth knowing in Scenic Rim

Section 5.7 states there is no building work regulated by the planning scheme, so sheds/carports, extensions, pools, fences and demolition are not assessable development under the scheme in the base case (a Building Act approval from a building certifier is still required) — EXCEPT where an overlay changes this (e.g. Airport Environs, Local Heritage, Flood, Landslide/Steep Slope overlays can make building work Accepted subject to requirements or code assessable). Local utility uses are Accepted in every zone and under every overlay. For subdivision, the 'minimum lot size' noted is the threshold at which ROL is code assessable rather than impact assessable; Low Density and Low-medium Density Residential zones rely on the minimum average lot size in Table 9.4.6.3.2 (not reproduced here) and Rural Residential/Rural thresholds depend on identification on Minimum Lot Size Overlay Map OM-13. Dual occupancy lot-size thresholds differ by precinct and by reticulated sewerage connection (e.g. Township Zone 2000m² sewered / 8000m² unsewered accepted-subject-to-requirements). Precincts are treated as separate zone rows where the scheme publishes a separate table of assessment. Transport Noise Corridor (OM-12), Minimum Lot Size (OM-13), Higher Order Road (OM-14), Road Hierarchy (OM-15), Flood Category Area (OM-6-B) and Streams and Dams (OM-10-B) overlays are information/administrative only and do not change the category of assessment.

What Scenic Rim Regional Council publishes

These come from the council's own website and planning scheme, read on 18 November 2026. Each one links to the page it came from. Councils change their rules and fees, so open the source before you rely on a figure.

Building application
Demolishing a structure needs a building application, lodged through a licensed building certifier. (Applies to: Any structure being demolished.) Demolishing, removal and relocating buildings (Scenic Rim Regional Council web page)
Check for planning approval first
Council asks owners to find out whether demolishing, removing or relocating a structure needs a planning approval before lodging any application, by contacting its Development Assessment and Engineering team. (Applies to: Demolition, removal or relocation of a structure.) Demolishing, removal and relocating buildings (Scenic Rim Regional Council web page)
Permit currency
A building permit for a removal or demolition has a currency period of 12 months, after which the application lapses. (Applies to: Building permits for removal or demolition.) Demolishing, removal and relocating buildings (Scenic Rim Regional Council web page)
Removal bond
For a removal or relocated building, council sets a removal bond once the preliminary removal application is approved, and the bond is payable before further approvals are issued. (Applies to: Structures being removed or relocated under a preliminary removal application.) Demolishing, removal and relocating buildings (Scenic Rim Regional Council web page)
Removal building referral fee 2026-27
The 2026-27 referral agency fee for a removal building is $2,087. (Applies to: Removal buildings referred to council as referral agency.) Register of Fees and Charges 2026-2027 (Scenic Rim Regional Council)
Asbestos disposal
Asbestos products are accepted at the landfill as a special burial, only with council approval and prior arrangement. (Applies to: Asbestos products (self haul domestic waste).) 2026-2027 Waste Charges Factsheet 1, Residential (Scenic Rim Regional Council)

The statewide rules

These apply across Queensland. Whether the council also needs to approve the demolition depends on your address: a heritage listing or a character overlay in the planning scheme is what brings it in.

Building approval
Demolishing a building is building work under the Building Act 1975, so it needs a building approval from a private certifier or the council. The regulation's list of work that needs no approval has no entry for demolishing a house.
Time limits
Once a demolition approval is given, the work must substantially start within 2 months and be finished within 1 year.
Local heritage places
Development on a place in a council's local heritage register is assessable across Queensland, so demolishing one needs a development application to the council.
Character and pre-war housing areas
There is no statewide rule. A council's planning scheme decides whether demolishing an older house in a character area needs a development application. Where a scheme does make demolishing a home assessable, a private certifier must hold the building approval documents for 5 business days before giving them to the applicant.
State heritage places
Any development on a place in the Queensland Heritage Register needs a development approval assessed by the State, unless an exemption certificate has been given. Exemption certificates are for work with little or no effect on the place.
Asbestos: licensed removal
A contractor needs an asbestos removal licence to remove more than 10 m² of bonded (non-friable) asbestos, and a class A licence for any friable asbestos. Asbestos must be removed before demolition starts, as far as is reasonably practicable.
Asbestos: doing it yourself
A homeowner can remove up to 10 m² of bonded asbestos. More than 10 m² needs a certificate from a Queensland Health-approved course. A homeowner can never remove friable asbestos.
Notice to Workplace Health and Safety Queensland
The contractor must give written notice at least 5 days before demolishing a structure that is at least 6 m high, or any demolition that uses load-shifting machinery on a suspended floor or explosives.
Sewer and water
Sealing the sewer drain of an existing building is notifiable plumbing work, done by a licensed plumber or drainer. Councils and water providers set their own disconnection steps and fees.
  • A building approval for demolition and a development application are separate. A certifier can't replace the council's decision where the planning scheme or a heritage listing requires one.

What else you'll need

  • Building approval

More about Scenic Rim

Other projects in Scenic Rim

Granny flatDual occupancySubdivideShed or carportExtensionPoolFence or wallHome businessTownhousesShop, café or officeClear trees

The statewide position on this project: Demolish in Queensland.

Read from the Scenic Rim Planning Scheme 2020 tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.