Swimming pools in Gladstone — do you need approval?

Gladstone Regional Council's planning scheme — the Gladstone Regional Council Planning Scheme (Version 2.1) — decides whether a swimming pool needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.

In a low density residential zone

No planning approval needed. A private swimming pool needs no planning development application in the Low density residential zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required).

I don't know my zone — choose my council instead

The zone is on your rates notice, or a Landbrief site report will find it for you.

Zone by zone

Building work (a swimming pool). Residential zones first.

ZoneWhat the table saysConditionsWhat you'll need
Low density residential zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Low density residential zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Low–medium density residential zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Low–medium density residential zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Medium density residential zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Medium density residential zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Character residential zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Character residential zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Rural residential zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Rural residential zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Emerging community zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Emerging community zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Township zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Township zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Centre zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Centre zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Community facilities zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Community facilities zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Conservation zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Conservation zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Environmental management zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Environmental management zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Industry investigation zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Industry investigation zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Limited development zone (constrained land) No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Limited development zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Low impact industry zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Low impact industry zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Major tourism zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Major tourism zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Medium impact industry zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Medium impact industry zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Minor tourism zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Minor tourism zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Mixed use zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Mixed use zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Neighbourhood centre zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Neighbourhood centre zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Open space zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Open space zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Principal centre zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Principal centre zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Rural zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Rural zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Special industry zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Special industry zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Special purpose zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Special purpose zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Specialised centre zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Specialised centre zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code
Sport and recreation zone No planning approval needed Section 5.7 A private swimming pool needs no planning development application in the Sport and recreation zone, because Gladstone's building work table makes no change to the category for building work on a dwelling house unless an overlay such as heritage applies (a building approval is still required). Building approval; Pool safety certificateAssessed against: Relevant zone code

Overlays that change the answer

  • Heritage overlay (local heritage place). On a local heritage place: a change of use that would be accepted subject to requirements and involves building work becomes code assessable; any building work not associated with a change of use (including minor work) is code assessable; demolition, partial demolition or removal is impact assessable; operational work changing landscaping, fencing or natural features named in the citation is code assessable. Work under a Queensland Heritage Act exemption certificate is accepted. (Table 5.10.1 Heritage overlay code)
  • Airport environs overlay. Any change of use, subdivision or building work becomes impact assessable if a structure intrudes above the Obstacle Limitation Surface, Transitional Surface or Approach and Departure Surface, and code assessable if within the ANEF 25–30 or 30–35 contour. (Table 5.10.1 Airport environs overlay code)

Worth knowing in Gladstone

Gladstone Regional Council Planning Scheme (Version 2.1), Part 5, converted from the council's PDF (not an official copy). A material change of use is impact assessable unless the table says otherwise or the use isn't listed; reconfiguring a lot is code assessable unless Table 5.6.1 says otherwise; building work and operational work are accepted unless the tables say otherwise (section 5.3.2). Building work (section 5.7): for a dwelling house there is 'no change to assessment category' against the relevant zone code, and no other building work is regulated unless an overlay table says so — so sheds, extensions, pools, fences and demolition need no planning development application outside overlays (mainly the Heritage overlay); a building approval under the Building Act is still needed. Accepted development subject to requirements that doesn't meet the listed acceptable outcomes becomes code assessable (section 5.3.3). Schedule 6 of the Planning Regulation (Table 5.4.1) can make a dwelling house or community residence accepted development regardless of the zone tables; Table 5.4.2 lets a one-into-two-lot subdivision in a residential or industry zone (not rural residential) be code assessable under schedule 10, part 12 of the Regulation against schedule 12 benchmarks. Precincts: Medium density residential — Beaches Village Circuit (dwelling house and dual occupancy impact assessable; 1,000 m² lots) and Gladstone West Hospital (shop/office/café code); Low density residential — Calliope neighbourhood (800 m² lots); Mixed use — Jeffery Court (office and some other uses lose their code/accepted pathway); Specialised centre — Clinton and Central Gladstone / Toolooa Street east (the only places retail/office uses are listed); Low impact industry — Hanson Road (showrooms, hardware); Medium impact industry — Red Rover Road (structure-plan pathway); Rural residential — Bicentennial Drive Enterprise; Sport and recreation — Benaraby Motor Sport; Special purpose — Gladstone Airport; Limited development — Flood affected lands (dwelling house code assessable, home based business accepted subject to requirements) and Major industry buffer. There are no local plans (section 5.9). Operational work: earthworks of 100 m³ or more are code assessable in all zones (Rural zone: 500 m³ for water retention, 100 m³ otherwise, accepted subject to requirements); the Coastal hazard and Flood hazard overlays make filling or excavation over 50 m³ code assessable. The Coastal hazard, Hazardous activities, Steep land, Scenic amenity and Water resource catchment overlays don't change the category but add their own acceptable outcomes to accepted development subject to requirements (code assessable if not met). Where land is in more than one zone or overlay, the highest category applies, and an overlay's category overrides the zone's (section 5.3.2).

What else you'll need

  • Building approval
  • Pool safety certificate

More about Gladstone

Other projects in Gladstone

Granny flatDual occupancySubdivideShed or carportExtensionFence or wallHome businessTownhousesShop, café or officeClear treesDemolish

The statewide position on this project: Pool in Queensland.

Read from the Gladstone Regional Council Planning Scheme (Version 2.1) tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.