Subdividing land in Scenic Rim — do you need approval?

Scenic Rim Regional Council's planning scheme — the Scenic Rim Planning Scheme 2020 — decides whether a subdivision needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.

In a low density residential zone

Needs a development application (code assessment). Subdividing is code-assessable when all new lots meet the zone's minimum lot size, otherwise an impact-assessable development application is required.

I don't know my zone — choose my council instead

The zone is on your rates notice, or a Landbrief site report will find it for you.

Zone by zone

Reconfiguring a lot. Residential zones first.

ZoneWhat the table saysConditionsWhat you'll need
Low Density Residential Zone Needs a development application (code assessment) Table 5.6.1 if all proposed residential lots meet the minimum average lot size in Table 9.4.6.3.2If not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Low Density Residential Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Low-medium Density Residential Zone Needs a development application (code assessment) Table 5.6.1 if all proposed residential lots meet the minimum average lot size in Table 9.4.6.3.2If not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Low-medium Density Residential Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Emerging Community Zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.6.1 Where involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The Planning Scheme
Rural Residential Zone - (Where no precinct applies) Minimum new lot 4,000 m² Needs a development application (code assessment) Table 5.6.1 if identified on Minimum Lot Size Overlay Map OM-13 and all proposed residential lots are 4000m² or greaterIf not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Rural Residential Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Rural Residential Zone - Rural Residential A Precinct Minimum new lot 1 ha Needs a development application (code assessment) Table 5.6.1 identified on Minimum Lot Size Overlay Map OM-13 and all proposed residential lots are 1ha or greaterIf not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Rural Residential Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Township Zone - (Where no precinct applies) Needs a development application (code assessment) Table 5.6.1 any reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Township Zone - Township Residential Precinct Needs a development application (code assessment) Table 5.6.1 Where involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Community Facilities Zone Needs a development application (code assessment) Table 5.6.1 Where involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Conservation Zone Needs a development application (code assessment) Table 5.6.1 Where involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
District Centre Zone Needs a development application (code assessment) Table 5.6.1 Where involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Industry Zone Needs a development application (code assessment) Table 5.6.1 all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Limited Development Zone - (Where no precinct applies) Needs a development application (code assessment) Table 5.6.1 all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Limited Development Zone - Flood Land Precinct Needs a development application (code assessment) Table 5.6.1 all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Limited Development Zone - Historical Subdivision Precinct Minimum new lot 2 ha Needs a development application (code assessment) Table 5.6.1 if all proposed lots are 2ha or greater (or 4000m² or greater in Harrisville)If not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Limited Development Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Local Centre Zone Needs a development application (code assessment) Table 5.6.1 any reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Major Centre Zone Needs a development application (code assessment) Table 5.6.1 any reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Major Tourism Zone Needs a development application (code assessment) Table 5.6.1 involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Minor Tourism Zone Needs a development application (code assessment) Table 5.6.1 involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Mixed Use Zone Needs a development application (code assessment) Table 5.6.1 involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Mixed Use Zone - Commercial Industry Precinct Needs a development application (code assessment) Table 5.6.1 involving all other reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Neighbourhood Centre Zone Needs a development application (code assessment) Table 5.6.1 Subdividing land in this zone is code assessable, so you need a development application assessed against the codes. Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Recreation and Open Space Zone - (Where no precinct applies) Needs a development application (code assessment) Table 5.6.1 Subdividing land in this zone is code assessable, so you need a development application assessed against the codes. Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Recreation and Open Space Zone - Passive Recreation Precinct Needs a development application (code assessment) Table 5.6.1 Subdividing land in this precinct is code assessable, so you need a development application assessed against the codes. Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Rural Zone - (Where no precinct applies) Minimum new lot 100 ha Needs a development application (code assessment) Table 5.6.1 all proposed lots 100ha or greater, or mapped on OM-13 meeting the 60ha or 40ha precinct minimumIf not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Rural Zone Code, Reconfiguration of a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Rural Zone - Rural Escarpment Protection Precinct Minimum new lot 100 ha Needs a development application (code assessment) Table 5.6.1 all proposed lots are 100ha or greaterIf not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Rural Zone Code, Reconfiguration of a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Rural Zone - Tamborine Mountain Rural Precinct Minimum new lot 100 ha Needs a development application (code assessment) Table 5.6.1 all proposed lots are 100ha or greaterIf not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Rural Zone Code, Reconfiguration of a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Special Purpose Zone - (Where no precinct applies) Needs a development application (code assessment) Table 5.6.1 any reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Special Purpose Zone - Bromelton State Development Area Precinct Needs a development application (code assessment) Table 5.6.1 any reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code
Special Purpose Zone - Bulk Water Storage Facilities Precinct Needs a development application (code assessment) Table 5.6.1 any reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: The relevant Zone Code, Reconfiguring a Lot Code, Earthworks, Construction and Water Quality Code, Infrastructure Design Code

Overlays that change the answer

  • Agricultural Land Overlay (OM-01). Reconfiguring a lot in Class A/B agricultural land or buffer area is code assessable against the Agricultural Land Overlay Code. Dwelling house, dual occupancy and home based business remain accepted in this overlay. (5.10 Agricultural Land Overlay Map OM-01)
  • Airport Environs and Defence Land Overlay (OM-02). Building work and material change of use in the Height Restriction Zone, Wildlife Buffer Area or Building Restricted Area become Accepted subject to requirements against the Airport Environs and Defence Land Overlay Code; other uses in the Defence Land Buffer Area and reconfiguring a lot become code assessable. (5.10 Airport Environs and Defence Land Overlay Map OM-02)
  • Bushfire Hazard Overlay (OM-03). Dwelling house/dual occupancy on a lot under 2000m² (residential zone) and domestic outbuildings stay accepted; otherwise a dwelling house or dual occupancy becomes Accepted subject to requirements, and other uses (and bed & breakfast/home childcare) become code assessable against the Bushfire Hazard Overlay Code. Reconfiguring a lot is code assessable. (5.10 Bushfire Hazard Overlay Map OM-03)
  • Environmental Significance Overlay - Biodiversity (OM-04-A). Material change of use and operational work (clearing) that is not exempt clearing in regulated vegetation or protected areas becomes code assessable against the Environmental Significance Overlay Code. Reconfiguring a lot in these areas is code assessable. (5.10 Environmental Significance Overlay Map - Biodiversity OM-04-A)
  • Environmental Significance Overlay - Local Biodiversity (OM-04-B). Non-exempt clearing / MCU in a core corridor, node corridor, stepping stone or critical linkage becomes code assessable. Reconfiguring a lot in these areas is code assessable. (5.10 Environmental Significance Overlay Map - Local Biodiversity OM-04-B)
  • Environmental Significance Overlay - Priority Species (OM-04-C). Non-exempt clearing / MCU in State Significant Species areas becomes code assessable. Reconfiguring a lot is code assessable. (5.10 Environmental Significance Overlay Map - Priority Species OM-04-C)
  • Environmental Significance Overlay - Wetlands and Waterways (OM-04-D). A dwelling house (and animal husbandry, cropping, home based business in an existing building) stays accepted; other MCU in Matters of State Environmental Significance waterways/wetlands becomes code assessable. Operational work above 10m³ or in high-value waters is code assessable. Reconfiguring a lot is code assessable. (5.10 Environmental Significance Overlay Map - Wetlands and Waterways OM-04-D)
  • Environmental Significance Overlay - Local Watercourses (OM-04-E). A dwelling house (and animal husbandry, cropping, home based business in an existing building) stays accepted in watercourse buffer areas; other MCU and non-exempt operational work become code assessable. Reconfiguring a lot is code assessable. (5.10 Environmental Significance Overlay Map - Local Watercourses OM-04-E)
  • Environmental Significance Overlay - Vegetation Management Area (OM-04-F). Non-exempt clearing / MCU in the Vegetation Management Area becomes code assessable against the Environmental Significance Overlay Code. Reconfiguring a lot is code assessable. (5.10 Environmental Significance Overlay Map - Vegetation Management Area OM-04-F)
  • Extractive Resources Overlay (OM-05). Animal husbandry and cropping stay accepted in a Key Resource Area; any other MCU becomes code assessable and reconfiguring a lot is code assessable against the Extractive Resources Overlay Code. (5.10 Extractive Resources Overlay Map OM-05)
  • Flood Hazard Overlay (OM-06-A). Only animal husbandry, cropping or roadside stall not involving building work stay accepted; any other use in a Flood Hazard Area (including a dwelling house) becomes code assessable against the Flood Hazard Overlay Code. Filling/excavation above the thresholds and non-exempt clearing are code assessable. Reconfiguring a lot is code assessable. (5.10 Flood Hazard Overlay Map - Hazard Area OM-06-A)
  • Landslide Hazard and Steep Slope Overlay - Steep Slope (OM-07-A). Domestic outbuildings stay accepted; a dwelling house, dual occupancy or home based business (not B&B/childcare) in a 15.1-25% slope area becomes Accepted subject to requirements, and any other use becomes code assessable against the Landslide Hazard and Steep Slope Overlay Code. Filling/excavation and vegetation clearing above thresholds are code assessable. Reconfiguring a lot is code assessable. (5.10 Landslide Hazard and Steep Slope Overlay Map - Steep Slope OM-07-A)
  • Landslide Hazard and Steep Slope Overlay - Landslide Hazard Area (OM-07-B). Animal husbandry, animal keeping and cropping not involving building work stay accepted; any other use in a Landslide Hazard Area becomes code assessable. Filling/excavation and vegetation clearing above thresholds are code assessable. Reconfiguring a lot is code assessable. (5.10 Landslide Hazard and Steep Slope Overlay Map - Landslide Hazard Area OM-07-B)
  • Local Heritage Overlay (OM-08). In a Local Heritage Place, material change of use, reconfiguring a lot, and building work or operational work not associated with an MCU all become code assessable against the Local Heritage Overlay Code (so renovations, outbuildings and demolition need a development application). (5.10 Local Heritage Overlay Map OM-08)
  • Regional Infrastructure Overlay (OM-09-A/OM-09-B). Animal husbandry and cropping stay accepted in the buffer areas/corridors; any other use becomes Accepted subject to requirements against the Regional Infrastructure Overlay Code, and reconfiguring a lot becomes code assessable. (5.10 Regional Infrastructure Overlay Map OM-09-B)
  • Water Resource Catchments Overlay (OM-10-A). A dwelling house, dual occupancy and home based business stay accepted in a water supply buffer/catchment area; most other uses become Accepted subject to requirements and listed higher-impact uses become code assessable against the Water Resource Catchments Overlay Code. Clearing of native vegetation (non-exempt) is Accepted subject to requirements, and reconfiguring a lot creating additional lots is code assessable. (5.10 Water Resource Catchments Overlay Map - Catchment Areas OM-10-A)
  • Master Plan Areas Overlay (OM-11). Reconfiguring a lot in a Master Plan Area becomes code assessable against the Master Plan Areas Overlay Code. (5.10 Master Plan Areas Overlay Map OM-11)

Worth knowing in Scenic Rim

Section 5.7 states there is no building work regulated by the planning scheme, so sheds/carports, extensions, pools, fences and demolition are not assessable development under the scheme in the base case (a Building Act approval from a building certifier is still required) — EXCEPT where an overlay changes this (e.g. Airport Environs, Local Heritage, Flood, Landslide/Steep Slope overlays can make building work Accepted subject to requirements or code assessable). Local utility uses are Accepted in every zone and under every overlay. For subdivision, the 'minimum lot size' noted is the threshold at which ROL is code assessable rather than impact assessable; Low Density and Low-medium Density Residential zones rely on the minimum average lot size in Table 9.4.6.3.2 (not reproduced here) and Rural Residential/Rural thresholds depend on identification on Minimum Lot Size Overlay Map OM-13. Dual occupancy lot-size thresholds differ by precinct and by reticulated sewerage connection (e.g. Township Zone 2000m² sewered / 8000m² unsewered accepted-subject-to-requirements). Precincts are treated as separate zone rows where the scheme publishes a separate table of assessment. Transport Noise Corridor (OM-12), Minimum Lot Size (OM-13), Higher Order Road (OM-14), Road Hierarchy (OM-15), Flood Category Area (OM-6-B) and Streams and Dams (OM-10-B) overlays are information/administrative only and do not change the category of assessment.

What Scenic Rim Regional Council publishes

These come from the council's own website and planning scheme, read on 18 November 2026. Each one links to the page it came from. Councils change their rules and fees, so open the source before you rely on a figure.

Application base fee 2026-27
The 2026-27 base fee for a reconfiguring a lot development application is $4,913, for both code and impact (consistent use) applications. A per lot fee is added. (Applies to: Reconfiguring a lot development applications.) Register of Fees and Charges 2026-2027 (Scenic Rim Regional Council)
Application per lot fee 2026-27
On top of the base fee, the 2026-27 code assessment fee for reconfiguring a lot is $1,055 per lot for the total number of lots. (Applies to: Code assessable reconfiguring a lot.) Register of Fees and Charges 2026-2027 (Scenic Rim Regional Council)
Survey plan signing fee 2026-27
The 2026-27 fee for council examination and signing of survey plans is $900 per lot. (Applies to: Standard format, building format and volumetric format plans for code and impact assessable development.) Register of Fees and Charges 2026-2027 (Scenic Rim Regional Council)
Infrastructure charge per new lot
Council's adopted infrastructure charge for reconfiguring a lot is $18,335.35 for each new lot under Charges Resolution Version No. 16 (27 August 2025), which the council lists as current. Water and sewerage charges are set separately by Urban Utilities. (Applies to: Each new lot, whole of the local government area.) Scenic Rim Regional Council Charges Resolution Version No.16, 27 August 2025, Table 2: Adopted charge - Reconfiguring a Lot

The statewide rules

These apply across Queensland. The minimum lot size and frontage come from the zone in your council's planning scheme, and an overlay can change how an application is assessed, so check your council and your address before you rely on them.

Minimum lot size
There is no statewide minimum. Each zone in each council's planning scheme sets its own, along with a minimum street frontage.
One lot into two
Statewide, splitting one lot into two is code assessable (no neighbour submissions) when the lot is in a residential or industry zone, it is not a rear lot, each new lot meets the zone's minimum size, and no overlay or flood, bushfire, landslide, storm tide or erosion-prone area covers any part of the land. Park residential and rural residential zones are excluded.
Neighbour submissions
An impact assessable application is publicly notified, and submissions stay open for at least 15 business days.
How long an approval lasts
An approval to reconfigure a lot lapses unless the survey plan is given to the council for approval within 4 years of the approval taking effect, or within the period the approval itself states.
Council sign-off on the survey plan
Titles Queensland can't register a plan that divides a lot until the council has approved it. The council must approve a plan that meets the criteria (the approval's conditions met or secured, no rates or charges owing, the plan matching the approval) and give notice within 20 business days.
Infrastructure charges
Councils charge for each new lot. From 1 July 2026 the most a council can charge is $38,029.25 for a home of 3 or more bedrooms and $27,163.80 for a home of 2 or fewer. Each council adopts its own charge up to that cap, and its charges resolution says how a vacant new lot is counted.
Registering the plan
Titles Queensland's 2026-27 fee to lodge a survey plan is $496.12, plus $36.49 for each lot on the plan.
Near a state road or railway
An application that adds a lot within 25 m of a state-controlled road, a railway or another state transport corridor is also referred to the State for assessment.
Rural land in South East Queensland
In the Regional Landscape and Rural Production Area of the South East Queensland regional plan, subdividing is prohibited unless every new lot is at least 100 hectares or the subdivision is one of the listed exemptions.
What needs no application
Joining two or more lots into one (amalgamation) is not assessable, and neither is a building format plan that doesn't divide the land itself. A scheme can't require an application for either.
  • The dollar figures are the 2026-27 amounts and change each 1 July.
  • Surveying, the roads and services the council's conditions require, and the council's own application and plan-sealing fees come on top. Council fees are on each council's page below.

What else you'll need

  • Survey plan
  • Infrastructure charges
  • Operational works

More about Scenic Rim

Other projects in Scenic Rim

Granny flatDual occupancyShed or carportExtensionPoolFence or wallHome businessTownhousesShop, café or officeClear treesDemolish

The statewide position on this project: Subdivide in Queensland.

Read from the Scenic Rim Planning Scheme 2020 tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.