Sheds, carports and garages in Moreton Bay — do you need approval?

City of Moreton Bay's planning scheme — the Moreton Bay Regional Council Planning Scheme 2016 (Version 8, 2026-09-11) — decides whether a shed, carport or garage needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.

In a general residential zone

No planning approval needed. A shed ancillary to a house is accepted if it meets the accepted criteria, otherwise accepted subject to requirements (a building approval is still needed).

I don't know my zone — choose my council instead

The zone is on your rates notice, or a Landbrief site report will find it for you.

Zone by zone

Building work (a domestic outbuilding). Residential zones first.

ZoneWhat the table saysConditionsWhat you'll need
General residential zone No planning approval needed Table 5.7.1 if complying with the circumstances for accepted development in Table 1.7.7.1If not met: accepted if you meet the requirements. Building approval (private certifier)Assessed against: 9.3.1 Dwelling house code
Emerging community zone Accepted if you meet the requirements Table 5.7.1 accepted if complying with Table 1.7.7.1 circumstances, otherwise accepted subject to requirements (Transition developed lot applies Dwelling house code) Building approval (private certifier)Assessed against: Relevant zone code (relevant precinct only)
Rural residential zone No planning approval needed Table 5.7.1 if complying with the circumstances for accepted development in Table 1.7.7.1If not met: accepted if you meet the requirements. Building approval (private certifier)Assessed against: 6.2.11 Rural residential zone code
Township zone No planning approval needed Table 5.7.1 in Township residential precinct, accepted if complying with Table 1.7.7.1; in centre/convenience precincts accepted subject to requirements in all instancesIf not met: accepted if you meet the requirements. Building approval (private certifier)Assessed against: 6.2.12 Township zone code
Centre zone Accepted if you meet the requirements Table 5.7.1 accepted if complying with Table 1.7.7.1 circumstances, otherwise accepted subject to requirements Building approval (private certifier)Assessed against: Relevant zone code (relevant precinct only)
Community facilities zone Accepted if you meet the requirements Table 5.7.1 accepted if complying with Table 1.7.7.1 circumstances, otherwise accepted subject to requirements Building approval (private certifier)Assessed against: Relevant zone code (relevant precinct only)
Environmental management and conservation zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.7.1 accepted only if on Council/State land per an approved plan or meeting Table 1.7.7.1 circumstances; otherwise impact Building approval (private certifier)Assessed against: The planning scheme
Extractive industry zone Accepted if you meet the requirements Table 5.7.1 if not complying with the circumstances for accepted development in Table 1.7.7.1If not met: no planning approval needed. Building approval (private certifier)Assessed against: Relevant zone code
Industry zone No planning approval needed Table 5.7.1 if complying with the circumstances for accepted development in Table 1.7.7.1If not met: accepted if you meet the requirements. Building approval (private certifier)Assessed against: Relevant zone code
Limited development zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.7.1 All building work not tied to a use change in the Limited development zone is impact assessable, so a shed needs an impact-assessable development application (plus a building approval). Building approval (private certifier)Assessed against: The planning scheme
Recreation and open space zone Accepted if you meet the requirements Table 5.7.1 building work not associated with a material change of use; accepted if it meets the circumstances in Table 1.7.7.1If not met: no planning approval needed. Building approval (private certifier)Assessed against: Relevant zone code
Rural zone No planning approval needed Table 5.7.1 if complying with the circumstances for accepted development in Table 1.7.7.1If not met: accepted if you meet the requirements. Building approval (private certifier)Assessed against: 6.2.10 Rural zone code

Overlays that change the answer

  • Coastal hazard overlay. In the Erosion Prone Area, Medium risk storm tide inundation area, or High risk storm tide inundation area a dwelling house (including a secondary dwelling) can become code assessable instead of accepted. Building work not associated with a material change of use stays as-is ('no change') if in the Balance coastal planning area, or in the Erosion Prone Area and not increasing gross floor area by more than 50m2; it becomes code assessable if in the Erosion Prone Area and increasing GFA by more than 50m2, or in a High/Medium risk storm tide inundation area, and impact assessable in the High risk area within the Limited development zone. Reconfiguring a lot by subdividing is assessed against the Coastal hazard overlay code. Filling/excavation can become code or impact assessable. (5.10.1 Coastal hazard overlay, Table 5.10.1.1)
  • Flood hazard overlay. A dwelling house (including a secondary dwelling) is code assessable in the High risk area, Medium risk area and Drainage investigation area (unless already impact assessable in the zone). Building work not associated with a material change of use is 'no change' in the Balance flood planning area, code assessable in the High risk area (not in Limited development zone), Medium risk area or Drainage investigation area, and impact assessable in the High risk area within the Limited development zone. Reconfiguring a lot by subdividing is code assessable (Flood hazard overlay code) or impact assessable in a Drainage investigation area. Filling/excavation can become code or impact assessable. (5.10.2 Flood hazard overlay, Table 5.10.2.1)

Worth knowing in Moreton Bay

The planning scheme's tables of assessment do not state numeric minimum lot sizes for reconfiguring a lot in any zone — the minimum lot size (and frontage) is set by the applicable 9.4.1 'Reconfiguring a lot code' for the relevant zone/precinct and the zone code, which are not reproduced in the Part 5 tables provided here. All reconfiguring a lot is code assessable 'if not otherwise specified' (impact assessment is the catch-all for anything not meeting the code's criteria). Separate state rules apply: Schedule 12 of the Planning Regulation makes reconfiguring a lot in Residential and Industry zones code assessable against the Schedule 12 benchmarks; a building approval under the Building Act is still required for building work even where the planning scheme treats it as accepted development; and the Vegetation Management Act may separately regulate clearing of native vegetation. Several zones are divided into precincts that materially change the answer for some projects — notably the Emerging community zone (Interim precinct vs Transition precinct developable lot vs developed lot, the latter mirroring the General residential Next generation neighbourhood precinct), the Community facilities zone precincts (where a Dwelling house is accepted subject to requirements and is NOT assessed under the Dwelling house code), and the Township zone precincts. In the Rural zone and Rural residential zone a Dwelling house is accepted development subject to requirements assessed under the relevant zone code (not the Dwelling house code). The Redcliffe Kippa-Ring local plan and Caboolture West local plan replace the base zone tables for land within those local plan areas and can change the category of development (e.g. in Caboolture West's Urban living precinct reconfiguring is impact assessable unless within an approved Neighbourhood Development Plan). Where more than one overlay applies, the highest category of assessment applies.

What City of Moreton Bay publishes

These come from the council's own website and planning scheme, read on 17 November 2026. Each one links to the page it came from. Councils change their rules and fees, so open the source before you rely on a figure.

Concurrence application fee 2026/27
Moreton Bay's 2026/27 fee for a Concurrence Application (not associated with a material change of use) is $1,035.00 per application, including one inspection. A minor change is $275.50. (Applies to: financial year 2026/27.) Development Services Fees and Charges Schedule 2026/27

The statewide rules

These are the statewide figures. A council's planning scheme can set its own, and an overlay can add more, so check your council and your address before you rely on them.

Shed with no building approval
A shed or similar structure with a plan area of no more than 10 m² (roof overhangs count), no higher than 2.4 m, with a mean height of no more than 2.1 m and no side longer than 5 m. It must still meet the boundary setbacks and the planning scheme.
Cyclone areas
That exemption doesn't apply in Wind Region C, the tropical cyclone area that takes in the coast of central and north Queensland. There, a shed of any size needs a building approval.
Carports and garages
A carport or garage is almost always larger than 10 m², so it needs a building approval from a private certifier or the council.
Side and rear boundaries
1.5 m for a structure up to 4.5 m high, and 2 m for the part between 4.5 m and 7.5 m high.
Building on or near the side or rear boundary
A shed, carport or garage can sit closer than 1.5 m, including on the boundary, when it is no higher than 4.5 m, the buildings within that strip total no more than 9 m along the boundary, and it is at least 1.5 m from a habitable-room window next door. Other conditions apply.
Street frontage
6 m from the road boundary on a lot of 450 m² or more, and 3 to 4 m on a smaller lot, depending on the street. An open carport can go inside that setback only when no other spot on the lot can comply.
Site cover
Roofed buildings, the house included, can cover no more than 50% of the lot.
Fire separation
A structure within 900 mm of a side or rear boundary may need fire-rated construction under the National Construction Code.
  • The boundary figures come from the Queensland Development Code, parts MP 1.1 (lots under 450 m²) and MP 1.2 (lots of 450 m² or more).
  • From 1 September 2026 the Queensland Housing Code replaces those parts, but only in a council area whose planning scheme has been amended to adopt it. The transition runs to 1 September 2029. Until a council adopts it, MP 1.1 and MP 1.2 still apply there.
  • A design that doesn't meet the figures isn't refused outright: the certifier refers it to the council, which assesses the siting against the code's performance criteria.

What else you'll need

  • Building approval (private certifier)

More about Moreton Bay

Other projects in Moreton Bay

Granny flatDual occupancySubdivideExtensionPoolFence or wallHome businessTownhousesShop, café or officeClear treesDemolish

The statewide position on this project: Shed or carport in Queensland.

Read from the Moreton Bay Regional Council Planning Scheme 2016 (Version 8, 2026-09-11) tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.