Subdividing land in Rockhampton — do you need approval?

Rockhampton Regional Council's planning scheme — the Rockhampton Region Planning Scheme 2015 (Version 5, 2025-03-28) — decides whether a subdivision needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.

In a low density residential zone

Needs a development application (code assessment). Subdividing land in this zone needs a code-assessed development application.

I don't know my zone — choose my council instead

The zone is on your rates notice, or a Landbrief site report will find it for you.

Zone by zone

Reconfiguring a lot. Residential zones first.

ZoneWhat the table saysConditionsWhat you'll need
Low density residential zone Needs a development application (code assessment) Table 5.5.1 all reconfiguring a lot in this zone Survey plan; Infrastructure charges; Operational worksAssessed against: Low density residential zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Low density residential zone — Fitzroy River accommodation precinct Needs a development application (code assessment) Table 5.5.1 all reconfiguring a lot in this zone Survey plan; Infrastructure charges; Operational worksAssessed against: Low density residential zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Low density residential zone — Residential stables precinct Needs a development application (code assessment) Table 5.5.1 all reconfiguring a lot in this zone Survey plan; Infrastructure charges; Operational worksAssessed against: Low density residential zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Low-medium density residential zone Needs a development application (code assessment) Table 5.5.1 all reconfiguring a lot in this zone Survey plan; Infrastructure charges; Operational worksAssessed against: Low-medium density residential zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
High density residential zone Needs a development application (code assessment) Table 5.5.1 Subdividing this land needs a code-assessed development application. Survey plan; Infrastructure charges; Operational worksAssessed against: High density residential zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Rural residential zone Needs a development application (code assessment) Table 5.5.1 Subdividing land in this zone needs a code-assessable development application against the relevant zone and reconfiguring codes. Survey plan; Infrastructure charges; Operational worksAssessed against: Rural residential zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Township zone Needs a development application (code assessment) Table 5.5.1 Subdividing land in the Township zone needs a code-assessable development application against the zone and reconfiguring codes. Survey plan; Infrastructure charges; Operational worksAssessed against: Township zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Emerging community zone Needs a development application (code assessment) Table 5.5.1 if any new lot is 10 hectares or greaterIf not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Emerging community zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code, The planning scheme
Community facilities zone Needs a development application (code assessment) Table 5.5.1 Subdividing land in the Community facilities zone needs a code-assessable development application. Survey plan; Infrastructure charges; Operational worksAssessed against: Relevant zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
District centre zone Needs a development application (code assessment) Table 5.5.1 Subdividing this land needs a code-assessed development application. Survey plan; Infrastructure charges; Operational worksAssessed against: District centre zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Environmental management and conservation zone Needs a development application (impact assessment — neighbours can make submissions) Table 5.5.1 Subdividing land in this zone always needs an impact-assessable development application. Survey plan; Infrastructure charges; Operational worksAssessed against: The planning scheme
High impact industry zone Needs a development application (code assessment) Table 5.5.1 All reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: Relevant zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Limited development (constrained land) zone Needs a development application (code assessment) Table 5.5.1 if the reconfiguring involves only a boundary realignmentIf not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Relevant zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Local centre zone Needs a development application (code assessment) Table 5.5.1 All reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: Local centre zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Low impact industry zone Needs a development application (code assessment) Table 5.5.1 All reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: Relevant zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Major centre zone Needs a development application (code assessment) Table 5.5.1 Subdividing this land needs a code-assessed development application. Survey plan; Infrastructure charges; Operational worksAssessed against: Major centre zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Medium impact industry zone Needs a development application (code assessment) Table 5.5.1 All reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: Relevant zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Neighbourhood centre zone Needs a development application (code assessment) Table 5.5.1 All reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: Neighbourhood centre zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Open space zone Needs a development application (code assessment) Table 5.5.1 All reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: Relevant zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Principal centre zone Needs a development application (code assessment) Table 5.5.1 Subdividing this land needs a code-assessed development application. Survey plan; Infrastructure charges; Operational worksAssessed against: Principal centre zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Rural zone Needs a development application (code assessment) Table 5.5.1 if any new lot meets the minimum lot size in the reconfiguring a lot code, or it is only a boundary realignmentIf not met: a development application with impact assessment (neighbours can make submissions). Survey plan; Infrastructure charges; Operational worksAssessed against: Rural zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Special industry zone Needs a development application (code assessment) Table 5.5.1 Subdividing land in the Special industry zone needs a code-assessable development application. Survey plan; Infrastructure charges; Operational worksAssessed against: Relevant zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Special purpose zone Needs a development application (code assessment) Table 5.5.1 Subdividing land in the Special purpose zone needs a code-assessable development application against the zone and reconfiguring codes. Survey plan; Infrastructure charges; Operational worksAssessed against: Special purpose zone code, Access, parking and transport code, Filling and excavation code, Landscape code, Reconfiguring a lot code, Stormwater management code, Water and sewer code
Specialised centre zone Needs a development application (code assessment) Table 5.5.1 All reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: Specialised centre zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Sport and recreation zone Needs a development application (code assessment) Table 5.5.1 All reconfiguring a lot Survey plan; Infrastructure charges; Operational worksAssessed against: Sport and recreation zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code
Waterfront and marine industry zone Needs a development application (code assessment) Table 5.5.1 Subdividing land in the Waterfront and marine industry zone needs a code-assessable development application. Survey plan; Infrastructure charges; Operational worksAssessed against: Relevant zone code, Reconfiguring a lot code, Access, parking and transport code, Filling and excavation code, Landscape code, Stormwater management code, Water and sewer code

Overlays that change the answer

  • Special management area overlay. Reconfiguring a lot that creates new lots becomes impact assessable; reconfiguring that creates no new lots is unchanged. (Table 5.9.10)
  • Acid sulfate soils overlay. No change to category, but the Acid sulfate soils overlay code applies to assessable development below 20m AHD involving significant excavation or filling. (Table 5.9.1)
  • Biodiversity overlay. No change to category, but the Biodiversity overlay code applies to assessable reconfiguring and operational work. (Table 5.9.3)
  • Water resource catchments overlay. No change to category, but the Water resource catchments overlay code applies to assessable development. (Table 5.9.12)

Worth knowing in Rockhampton

IMPORTANT: The scheme's building work table (section 5.6) is 'Not applicable' — the scheme does NOT itself make domestic building work (sheds, carports, pools, fences, extensions, demolition) assessable in the base case. Those projects are generally 'accepted' under the planning scheme (no planning development application), but a building approval under the Building Act 1975 is almost always still required and must be obtained separately. Overlays (especially Flood, Character, Heritage) can change this — see overlay_triggers. Granny flats: the QPP 'Dwelling house' definition includes a secondary dwelling, so a granny flat follows the Dwelling house row of each zone; in residential/township/rural/rural residential/emerging community zones a dwelling house is 'accepted' (or 'accepted subject to requirements' in Emerging community and Rural), but in centre, industry, open space, sport & recreation, community facilities, special purpose, limited development and environmental zones a dwelling house is not listed and falls to the 'any other use' row = impact assessable. Minimum lot sizes for subdivision are set in Table 9.3.5.3.2 of the Reconfiguring a lot code, which was not reproduced in the material provided — specific numeric minimums per zone could not be extracted, so min_lot_size_m2 is null for all zones. Known thresholds: Emerging community = 10 hectares for code assessment; Rural = the minimum nominated in the Reconfiguring a lot code. Many zones have precincts and sub-precincts; the scheme states that for a precinct/sub-precinct the relevant (parent) zone categories apply for reconfiguring and operational work, but material-change-of-use tables can differ by precinct (e.g. Low density residential Fitzroy River accommodation precinct allows some small-scale commercial uses). Tree clearing: the scheme only regulates vegetation clearing as operational work via overlays (Biodiversity, etc.); the general operational work table (5.7.1) mainly covers filling/excavation and access/services works — most vegetation clearing is accepted under the scheme but the State Vegetation Management Act 1999 rules are separate and may still apply. Home-based business is 'accepted subject to requirements' in residential, township, rural, rural residential, industry and emerging community zones (meet the relevant zone code) and 'accepted' in centre zones.

What Rockhampton Regional Council publishes

These come from the council's own website and planning scheme, read on 18 November 2026. Each one links to the page it came from. Councils change their rules and fees, so open the source before you rely on a figure.

Application fee 2026-27
The 2026-27 reconfiguring a lot (subdivision) application fee is $2,542.00 per application plus $785.00 per lot. (Applies to: All reconfiguring a lot (subdivision) applications.) 2026/2027 Fees and Charges: Development Advice Centre including Building, Plumbing and Drainage (Rockhampton Regional Council, as at 14 July 2026)
Survey plan endorsement fee 2026-27
The 2026-27 fee to submit a survey plan for endorsement is $785.00 per application plus $277.00 per lot. (Applies to: Survey plans lodged with Council for endorsement.) 2026/2027 Fees and Charges: Development Advice Centre including Building, Plumbing and Drainage (Rockhampton Regional Council, as at 14 July 2026)
Infrastructure charge per lot
The base infrastructure charge for reconfiguring a lot is $38,029.25 per lot, under Charges Resolution No. 3 (2026), which has effect from 1 October 2026. (Applies to: Each lot that places demand on trunk infrastructure.) Charges Resolution No. 3 (2026) (Rockhampton Regional Council, effect from 1 October 2026)

The statewide rules

These apply across Queensland. The minimum lot size and frontage come from the zone in your council's planning scheme, and an overlay can change how an application is assessed, so check your council and your address before you rely on them.

Minimum lot size
There is no statewide minimum. Each zone in each council's planning scheme sets its own, along with a minimum street frontage.
One lot into two
Statewide, splitting one lot into two is code assessable (no neighbour submissions) when the lot is in a residential or industry zone, it is not a rear lot, each new lot meets the zone's minimum size, and no overlay or flood, bushfire, landslide, storm tide or erosion-prone area covers any part of the land. Park residential and rural residential zones are excluded.
Neighbour submissions
An impact assessable application is publicly notified, and submissions stay open for at least 15 business days.
How long an approval lasts
An approval to reconfigure a lot lapses unless the survey plan is given to the council for approval within 4 years of the approval taking effect, or within the period the approval itself states.
Council sign-off on the survey plan
Titles Queensland can't register a plan that divides a lot until the council has approved it. The council must approve a plan that meets the criteria (the approval's conditions met or secured, no rates or charges owing, the plan matching the approval) and give notice within 20 business days.
Infrastructure charges
Councils charge for each new lot. From 1 July 2026 the most a council can charge is $38,029.25 for a home of 3 or more bedrooms and $27,163.80 for a home of 2 or fewer. Each council adopts its own charge up to that cap, and its charges resolution says how a vacant new lot is counted.
Registering the plan
Titles Queensland's 2026-27 fee to lodge a survey plan is $496.12, plus $36.49 for each lot on the plan.
Near a state road or railway
An application that adds a lot within 25 m of a state-controlled road, a railway or another state transport corridor is also referred to the State for assessment.
Rural land in South East Queensland
In the Regional Landscape and Rural Production Area of the South East Queensland regional plan, subdividing is prohibited unless every new lot is at least 100 hectares or the subdivision is one of the listed exemptions.
What needs no application
Joining two or more lots into one (amalgamation) is not assessable, and neither is a building format plan that doesn't divide the land itself. A scheme can't require an application for either.
  • The dollar figures are the 2026-27 amounts and change each 1 July.
  • Surveying, the roads and services the council's conditions require, and the council's own application and plan-sealing fees come on top. Council fees are on each council's page below.

What else you'll need

  • Survey plan
  • Infrastructure charges
  • Operational works

More about Rockhampton

Other projects in Rockhampton

Granny flatDual occupancyShed or carportExtensionPoolFence or wallHome businessTownhousesShop, café or officeClear treesDemolish

The statewide position on this project: Subdivide in Queensland.

Read from the Rockhampton Region Planning Scheme 2015 (Version 5, 2025-03-28) tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.