Demolishing a building in Bundaberg — do you need approval?
Bundaberg Regional Council's planning scheme — the Bundaberg Regional Council Planning Scheme 2015 — decides whether demolition needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.
In a low density residential zone
No planning approval needed. Bundaberg's building work table doesn't list demolition, so it falls under the 'accepted if not subject to requirements' row and needs no planning development application (a building approval is still needed, and demolishing a local heritage place or a Victorian, Federation or Interwar building in a neighbourhood character area needs a code assessable development application).
I don't know my zone — choose my council instead
The zone is on your rates notice, or a Landbrief site report will find it for you.
Zone by zone
Building work (demolition). Residential zones first.
| Zone | What the table says | Conditions | What you'll need |
|---|---|---|---|
| Low density residential zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Medium density residential zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| High density residential zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Rural residential zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Emerging community zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Community facilities zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| District centre zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Environmental management and conservation zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| High impact industry zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Industry zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Limited development zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Local centre zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Major centre zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Neighbourhood centre zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Open space zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Principal centre zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Rural zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Special purpose zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Specialised centre zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
| Sport and recreation zone | No planning approval needed Table 5.6.1 | demolition is not listed as building work subject to requirements | Building approval |
Overlays that change the answer
- Heritage and neighbourhood character overlay (local heritage place). Building work that alters, demolishes, relocates or removes a local heritage place is code assessable, and so is a change of use (otherwise accepted or accepted subject to requirements) that results in such building work. Development next door to a heritage place keeps its category. (Table 5.9.1 Heritage and neighbourhood character overlay – heritage place)
- Heritage and neighbourhood character overlay (neighbourhood character area). Demolishing, relocating or removing a Victorian, Federation or Interwar building, or extending it in front of or visibly from the street, enclosing a front verandah, changing front/side cladding or raising it, is code assessable; a change of use involving building work (other than an internal fit-out) that would otherwise be accepted or accepted subject to requirements is code assessable. (Table 5.9.1 Heritage and neighbourhood character overlay – neighbourhood character area)
Worth knowing in Bundaberg
Bundaberg Regional Council Planning Scheme 2015 (Version 6.6, effective 31 July 2026), Part 5. A material change of use is impact assessable unless the table says otherwise or the use isn't listed; reconfiguring a lot is code assessable unless Table 5.5.1 says impact (Low density residential, Rural and Rural residential below the minimum lot size; Emerging community and Limited development zones generally); building and operational work are accepted unless the tables say otherwise (section 5.3.2). Accepted development subject to requirements that doesn't meet the nominated acceptable outcomes becomes code assessable (section 5.3.3). A dwelling house includes a secondary dwelling (granny flat); Schedule 6 of the Planning Regulation 2017 can make a dwelling house accepted regardless of these tables. Building work for a dwelling house (sheds, extensions, pools, fences) is accepted subject to the Dwelling house code and Transport and parking code in all zones (Table 5.6.1); a building approval under the Building Act is still needed. Vegetation clearing that isn't 'exempt vegetation clearing' (Schedule 1) is code assessable against the Vegetation management code in every zone (Table 5.7.1); state Vegetation Management Act rules apply separately. Excavation or filling over 50 m³ (or filling over 10 m³ / 150 mm average depth, or excavation deeper than 1 m) is code assessable unless on Rural zoned land for a rural activity. Minimum lot sizes live in Table 9.3.4.3.2 of the Reconfiguring a lot code, which isn't in Part 5. Precincts: Medium density residential MDRZ1 (Bundaberg West medical/health hub) and MDRZ2 (Barolin Street office precinct); Principal centre PCZ2 (City centre riverfront) and PCZ3 (City centre frame); Limited development LDZ1 (Limited residential); District centre rows differ for Childers and Gin Gin; Local centre short-term accommodation/resort rows apply in Bargara. Community facilities zone: a use annotated on the zone map is accepted (footprint unchanged) or code assessable. Special purpose zone: development in the Bundaberg State Development Area is decided by the Coordinator-General and Strategic Port Land by the Port Authority. Local plan: the Bundaberg Health and Enterprise Precinct local plan (Table 5.8.1, Emerging community zone land) overrides the zone — in its Low-Medium Density Residential Precinct a dwelling house, dual occupancy and home based business are accepted subject to requirements and a multiple dwelling of up to three dwellings on a lot of at least 600 m² is accepted subject to requirements (code otherwise); in its Medium-High Density Residential Precinct dual occupancy, home based business and multiple dwelling are code assessable; shops, cafés and offices are accepted subject to requirements or code assessable in the Health and Knowledge Sub-Precincts; reconfiguring a lot is code assessable in its Health and Knowledge, residential and Parkland precincts. Overlays (Table 5.9.1): most overlays only add the overlay code as a benchmark without changing the category (acid sulfate soils, agricultural land, biodiversity areas, bushfire hazard, coastal management district/erosion prone area/setback line, extractive transport route, gas pipeline and electricity buffers, steep land, water resource catchments). Overlays that do change the category are in overlay_triggers: airport operational airspace, public safety area and building restricted area; sea turtle sensitive area (over-height development becomes impact); extractive resource/processing and separation areas; flood hazard (not for a dwelling house); local heritage places and neighbourhood character areas (alterations and demolition become code assessable); and infrastructure buffers (wastewater, waste, road/rail/cane rail corridors). The airport lighting and wildlife hazard buffers make specific uses (putrescible waste, aquaculture, abattoirs, intensive animal industry, showgrounds, constructed waterbodies) code assessable, and excavation or filling in a flood hazard area, gas pipeline buffer or on steep land becomes code assessable. Where premises are in more than one zone, local plan or overlay, the highest category applies to the part affected.
What Bundaberg Regional Council publishes
These come from the council's own website and planning scheme, read on 18 November 2026. Each one links to the page it came from. Councils change their rules and fees, so open the source before you rely on a figure.
- Removal of a building: referral to council
- A building application to remove a building or other structure from a site, whether or not it is rebuilt elsewhere, needs referral to the council as a referral agency. (Applies to: Building work for removal of a building or structure, or rebuilding of one removed from another site, anywhere in the Bundaberg Regional Council area.) Amenity and Aesthetics and Removal or Rebuilding Policy, Version 1 (Bundaberg Regional Council, adopted 28/04/2026)
- No security bond for removal or rebuilding
- The council does not require a security bond for building work for removal or rebuilding of a building. (Applies to: Removal or rebuilding referrals under the 2026 policy.) Amenity and Aesthetics and Removal or Rebuilding Policy, Version 1 (Bundaberg Regional Council, adopted 28/04/2026)
- Site condition after removal
- Standard referral conditions for removing a building include taking all debris off the site, including remaining stumps, foundations, plumbing fixtures and wastewater treatment systems, and leaving the ground level. (Applies to: Removal of a building or structure referred to the council.) Amenity and Aesthetics and Removal or Rebuilding Policy, Version 1 (Bundaberg Regional Council, adopted 28/04/2026)
- Local heritage place: demolition
- Most building work involving the demolition, relocation or removal of a local heritage place needs a development application to the council. (Applies to: Local heritage places (Heritage and neighbourhood character overlay), other than minor works under an exemption certificate.) Heritage properties (Bundaberg Regional Council web page)
- Neighbourhood character area: demolition
- In a neighbourhood character area, building work involving the demolition, relocation or removal of a Victorian, Federation or Interwar building or structure needs a development application to the council. (Applies to: Properties in a neighbourhood character area of the Heritage and neighbourhood character overlay.) Heritage properties (Bundaberg Regional Council web page)
- Asbestos disposal at council tips
- The 2026/27 charge for asbestos and material containing asbestos is $208 per tonne. It has to be correctly wrapped and only waste generated within the Bundaberg local government area is accepted. (Applies to: Asbestos sheeting, pipes and similar taken to council waste facilities.) Bundaberg Regional Council Fees and Charges 2026/27
The statewide rules
These apply across Queensland. Whether the council also needs to approve the demolition depends on your address: a heritage listing or a character overlay in the planning scheme is what brings it in.
- Building approval
- Demolishing a building is building work under the Building Act 1975, so it needs a building approval from a private certifier or the council. The regulation's list of work that needs no approval has no entry for demolishing a house.
- Time limits
- Once a demolition approval is given, the work must substantially start within 2 months and be finished within 1 year.
- Local heritage places
- Development on a place in a council's local heritage register is assessable across Queensland, so demolishing one needs a development application to the council.
- Character and pre-war housing areas
- There is no statewide rule. A council's planning scheme decides whether demolishing an older house in a character area needs a development application. Where a scheme does make demolishing a home assessable, a private certifier must hold the building approval documents for 5 business days before giving them to the applicant.
- State heritage places
- Any development on a place in the Queensland Heritage Register needs a development approval assessed by the State, unless an exemption certificate has been given. Exemption certificates are for work with little or no effect on the place.
- Asbestos: licensed removal
- A contractor needs an asbestos removal licence to remove more than 10 m² of bonded (non-friable) asbestos, and a class A licence for any friable asbestos. Asbestos must be removed before demolition starts, as far as is reasonably practicable.
- Asbestos: doing it yourself
- A homeowner can remove up to 10 m² of bonded asbestos. More than 10 m² needs a certificate from a Queensland Health-approved course. A homeowner can never remove friable asbestos.
- Notice to Workplace Health and Safety Queensland
- The contractor must give written notice at least 5 days before demolishing a structure that is at least 6 m high, or any demolition that uses load-shifting machinery on a suspended floor or explosives.
- Sewer and water
- Sealing the sewer drain of an existing building is notifiable plumbing work, done by a licensed plumber or drainer. Councils and water providers set their own disconnection steps and fees.
- A building approval for demolition and a development application are separate. A certifier can't replace the council's decision where the planning scheme or a heritage listing requires one.
- Building Act 1975, sections 5 (building work), 20 (assessable building work), 71 (time limits for demolition) and 88 (the 5 business day hold)
- Planning Regulation 2017, Schedule 10, sections 14 (local heritage places) and 15 (Queensland heritage places)
- Work Health and Safety Regulation 2011, sections 142 (notice of demolition work), 452, 458, 485 and 487 (asbestos)
- Public Health Regulation 2018, sections 7 and 8 — asbestos removal by homeowners
- Homeowner's certificate to remove asbestos — Queensland Government
- Plumbing and Drainage Regulation 2019, Schedule 1 — notifiable work
What else you'll need
- Building approval
More about Bundaberg
- What can you build in Bundaberg? Council overview and development applications
- Every Queensland zone explained, with what each council allows and the planning overlays that change the answer
- What Bundaberg Regional Council charges for a development application, compared with other councils
- A Landbrief site report for your Bundaberg address — every planning layer that applies to the lot
- Development applications in Bargara
- Development applications in Innes Park
- Development applications in Burnett Heads
- Development applications in Branyan
- Development applications in Woodgate
- Development applications in Elliott Heads
- Development applications in Moore Park Beach
- Development applications in Gooburrum
Other projects in Bundaberg
Granny flatDual occupancySubdivideShed or carportExtensionPoolFence or wallHome businessTownhousesShop, café or officeClear trees
The statewide position on this project: Demolish in Queensland.
Read from the Bundaberg Regional Council Planning Scheme 2015 tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.