Demolishing a building in Noosa — do you need approval?
Noosa Shire Council's planning scheme — the Noosa Plan 2020 — decides whether demolition needs a development application, and the answer depends on the zone your property is in. Below is what its table of assessment says for each zone; or check your own address.
In a low density residential
Needs a development application (code assessment). Noosa makes demolishing or removing a building code assessable in every zone, so a development application is needed (assessed against the Waste Management and Water Quality and Drainage codes) as well as a building approval.
I don't know my zone — choose my council instead
The zone is on your rates notice, or a Landbrief site report will find it for you.
Zone by zone
Building work (demolition). Residential zones first.
| Zone | What the table says | Conditions | What you'll need |
|---|---|---|---|
| Low Density Residential | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Medium Density Residential | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| High Density Residential | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Tourist Accommodation | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Rural Residential | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Community Facilities | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| District Centre | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Environmental Management and Conservation | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Innovation Zone | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Local Centre | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Low Impact Industry | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Major Centre | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Medium Impact Industry | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Neighbourhood Centre | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Recreation and Open Space | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
| Rural | Needs a development application (code assessment) Table 5.7.1 | building work for removal or demolition of a building not associated with a material change of use | Building approvalAssessed against: Waste Management Code, Water Quality and Drainage Code |
Overlays that change the answer
- Heritage Overlay. Demolition, relocation or removal of a building, and reconfiguring a lot, are code assessable against the Heritage Overlay Code. (Table 5.9.7 Heritage Overlay)
Worth knowing in Noosa
Noosa Plan 2020 (Amendment 3, effective 20 March 2026), Part 5. A material change of use is impact assessable unless the table says otherwise or the use isn't listed; reconfiguring a lot is code assessable in every zone (Table 5.6.1); building work and operational work are accepted unless the tables say otherwise. Noosa makes demolition or removal of any building code assessable in all zones (Table 5.7.1), unusually. Building work for a dwelling house or a Class 10 structure (shed, carport, pool, fence) is accepted subject to requirements in the Low, Medium and High Density Residential, Tourist Accommodation, Rural Residential and Rural zones; in all other zones building work is accepted only inside an existing building with no new buildings or expansion, otherwise code assessable. A building approval under the Building Act is still needed in all cases. Accepted development subject to requirements that doesn't meet the listed acceptable outcomes becomes code assessable (section 5.3.3). A dwelling house includes a secondary dwelling (granny flat); in the Medium and High Density Residential zones a dwelling house is only listed for lots under 500 m², so on bigger lots the 'any other use' impact row applies. Schedule 6, Part 2 of the Planning Regulation 2017 can make a dwelling house, community residence, home-based business or rooming accommodation accepted regardless of these tables. Precincts: the Major Centre (Noosa Junction Hospitality; Noosa Business Centre Showroom, Business Park, Retail, Village Mixed Use), District Centre (Mary/Thomas Street Health and Wellbeing, Doonella Street, Noosaville Mainstreet), Low Impact Industry (Lionel Donovan Drive Auto, Hofmann Drive, Factory Street, Kin Kin, Gateway West Makers) and Medium Impact Industry (Venture Drive Enterprise) zones have precinct tables that vary some uses; the 'Where not located in a Precinct' tables are empty on the ePlan, so the parent zone table applies outside precincts. The Major Centre page labels its own table 'Table 5.5.1' (a typo) — it is Table 5.5.5. Many rows are tied to named lots or streets (e.g. 99 Noosa Drive, Gympie Terrace, Hastings Street) — check the conditions. Where premises are in more than one zone or overlay, the highest category applies to the part affected. Operational work for a dwelling driveway is accepted subject to the Low Density Housing Code; excavation or filling over 10 m³ (residential and environmental zones) or 100 m³ (other zones) is code assessable. Vegetation clearing benchmarks sit in the Biodiversity, Waterways and Wetlands Overlay Code; state Vegetation Management Act rules apply separately.
What Noosa Shire Council publishes
These come from the council's own website and planning scheme, read on 18 November 2026. Each one links to the page it came from. Councils change their rules and fees, so open the source before you rely on a figure.
- Demolition development application fee 2026-27
- The 2026-27 fee for a development application for building works (demolition) assessable against the planning scheme is $1,598. (Applies to: Demolition that is assessable against the planning scheme.) Fees and Charges 2026-27 (Noosa Shire Council)
- Removal or rebuilding referral fee 2026-27
- The 2026-27 fee for a concurrence agency referral to council for building work for removal or rebuilding is $1,168. (Applies to: Building work for removal or rebuilding referred to council as concurrence agency.) Fees and Charges 2026-27 (Noosa Shire Council)
- Asbestos disposal
- Asbestos can be disposed of at the Noosa Resource Recovery Centre only, and the Asbestos Disposal form must be submitted 2 business days before disposal. (Applies to: Asbestos waste.) Asbestos Risk (Noosa Shire Council web page)
- Asbestos disposal charge 2026-27
- The 2026-27 asbestos disposal charge is $335 pro rata per tonne or cubic metre, and the application fee to dispose of regulated waste such as asbestos is from $104. (Applies to: Asbestos taken to the Eumundi Road landfill (Noosa Resource Recovery Centre).) Waste Disposal Charges (Inc GST) 2026-2027 (Noosa Shire Council)
The statewide rules
These apply across Queensland. Whether the council also needs to approve the demolition depends on your address: a heritage listing or a character overlay in the planning scheme is what brings it in.
- Building approval
- Demolishing a building is building work under the Building Act 1975, so it needs a building approval from a private certifier or the council. The regulation's list of work that needs no approval has no entry for demolishing a house.
- Time limits
- Once a demolition approval is given, the work must substantially start within 2 months and be finished within 1 year.
- Local heritage places
- Development on a place in a council's local heritage register is assessable across Queensland, so demolishing one needs a development application to the council.
- Character and pre-war housing areas
- There is no statewide rule. A council's planning scheme decides whether demolishing an older house in a character area needs a development application. Where a scheme does make demolishing a home assessable, a private certifier must hold the building approval documents for 5 business days before giving them to the applicant.
- State heritage places
- Any development on a place in the Queensland Heritage Register needs a development approval assessed by the State, unless an exemption certificate has been given. Exemption certificates are for work with little or no effect on the place.
- Asbestos: licensed removal
- A contractor needs an asbestos removal licence to remove more than 10 m² of bonded (non-friable) asbestos, and a class A licence for any friable asbestos. Asbestos must be removed before demolition starts, as far as is reasonably practicable.
- Asbestos: doing it yourself
- A homeowner can remove up to 10 m² of bonded asbestos. More than 10 m² needs a certificate from a Queensland Health-approved course. A homeowner can never remove friable asbestos.
- Notice to Workplace Health and Safety Queensland
- The contractor must give written notice at least 5 days before demolishing a structure that is at least 6 m high, or any demolition that uses load-shifting machinery on a suspended floor or explosives.
- Sewer and water
- Sealing the sewer drain of an existing building is notifiable plumbing work, done by a licensed plumber or drainer. Councils and water providers set their own disconnection steps and fees.
- A building approval for demolition and a development application are separate. A certifier can't replace the council's decision where the planning scheme or a heritage listing requires one.
- Building Act 1975, sections 5 (building work), 20 (assessable building work), 71 (time limits for demolition) and 88 (the 5 business day hold)
- Planning Regulation 2017, Schedule 10, sections 14 (local heritage places) and 15 (Queensland heritage places)
- Work Health and Safety Regulation 2011, sections 142 (notice of demolition work), 452, 458, 485 and 487 (asbestos)
- Public Health Regulation 2018, sections 7 and 8 — asbestos removal by homeowners
- Homeowner's certificate to remove asbestos — Queensland Government
- Plumbing and Drainage Regulation 2019, Schedule 1 — notifiable work
What else you'll need
- Building approval
More about Noosa
- What can you build in Noosa? Council overview and development applications
- Every Queensland zone explained, with what each council allows and the planning overlays that change the answer
- What Noosa Shire Council charges for a development application, compared with other councils
- A Landbrief site report for your Noosa address — every planning layer that applies to the lot
- Development applications in Noosa Heads
- Development applications in Noosaville
- Development applications in Cooroy
- Development applications in Peregian Beach
- Development applications in Pomona
- Development applications in Lake Macdonald
- Development applications in Sunshine Beach
- Development applications in Tewantin
Other projects in Noosa
Granny flatDual occupancySubdivideShed or carportExtensionPoolFence or wallHome businessTownhousesShop, café or officeClear trees
The statewide position on this project: Demolish in Queensland.
Read from the Noosa Plan 2020 tables of assessment. General information, not advice. The council's planning scheme and the Planning Act 2016 decide — confirm with the council or a town planner before you build.